Project implementation progress in May 2012.
By the end of May 2012, Vinaconex-ITC is implementing the following items of the project:
  • Completed the roads of IB phase;
  • Completed water supply-drainage system of IB phase;
  • Completed river embankments of IB phase and river embankment of Moonia Hotel;
  • Completed transformer station and install step-down transformer of IB phase;
  • Construct river embankments of IIA, IIB phases;
  • Started building villas of B2,B3 component.
Some pictures of the site:






Construct river embankments of IIA, IIB phases




Planting trees of B5

This series of photos villas B2, B3