Project implementation progress in April 2012.
By the end of April 2012, Vinaconex-ITC is implementing the following items of the project:

-    Completed the roads of IB phase;
-    Completed water supply-drainage system of IB phase;
-    Completed river embankments of IB phase and river embankment of Moonia Hotel;
-    Completed transformer station and install step-down transformer of IB phase;
-    Construct river embankments of IIA, IIB phases;
-    Started building villas of B2,B3 component.

Some pictures of the site:


Construction water-drainage system of IB phase.
 



Construct river embankments of IIA, IIB phases
  




Planting trees of B5
 
This series of photos villas B2, B3