Project implementation progress in February 2012.
By the end of February 2012, Vinaconex-ITC is implementing the following items of the project:

-    Completed the roads of IB phase;
-    Completed water supply-drainage system of IB phase;
-    Completed river embankments of IB phase and river embankment of Moonia Hotel;
-    Completed transformer station and install step-down transformer of IB phase;
-    Construct river embankments of IIA, IIB phases;
-    Started building villas of B2,B3 component.

Some pictures of the site:



Construction of embankments foundation stone ranked phase IIA, IIB.
 




Overview of project.
Building villa B2-1

Building villa B2-2
 

Building villa B2-15
Building villa B3-22
Building villa B2-63

Building villa B2-39



Route 74-79A
 