Project implementation progress in December 2011
By the end of December 2011, Vinaconex-ITC is implementing the following items of the project:
- Construct the roads of IB phase;
- Construct water supply-drainage system of IB phase;
- Construct river embankments of IB phase and river embankment of Moonia Hotel;
- Construct transformer station and install step-down transformer of IB phase;
- Construct river embankments of IIA, IIB phases; - Construct villa bases of II phase;
- Started building villas of B2,B3 component.

Some pictures of the site:


Construct water supply-drainage system of IB phase.

Construct river embankments of Moonia Hotel.

Construct of sidewalks paved road to the C2 bridge.

Construct of drain repaired.


Building villa B2-2





Building villa B2-15





Building villa B2-25



Building villa B2-30


Overview of B2
  