Project implementation progress in January 2012.
By the end of January 2012, Vinaconex-ITC is implementing the following items of the project:

-    Completed the roads of IB phase;
-    Completed water supply-drainage system of IB phase;
-    Completed river embankments of IB phase and river embankment of Moonia Hotel;
-    Completed transformer station and install step-down transformer of IB phase;
-    Construct river embankments of IIA, IIB phases;
-    Construct villa bases of C2 Zone;
-    Started building villas of B2,B3 component.

Some pictures of the site:

The C2 bride


Cleaning up in construction


Construct river embankments of IIA,IIB.




N20  Intersection


Tree planting


Building villa B2-2

Building villa B2-15


Building villa B2-25






Building villa B2-39